Development timeline

July 2019

  • multi-use steel structure (complete)
  • electrical service (complete)


August 2019

  • install well/pump (complete)


August 2019 until completion

  • frame vet exam room and office  (complete)
  • install plumbing and septic (underway)


October 2019

  • interior room drywall, floor and ceiling installation (underway)
  • removal of FLEPPC class I and class II invasives (complete, ongoing)
  • begin wildlife habitat enhancement (started, ongoing)


October 2019 - March 2020

  • build dog, cat, and parrot housing / habitats (delayed)
  • enhance pond and turtle habitat (underway)
  • install utilities as necessary (underway)


April 2020

  • relocation of resident property manager


May 2020

  • open for business...

image3